Coal Combustion Residuals (CCR) Rule Compliance Data and Information
Operating Criteria
- CCR Fugitive Dust Control Plan (amended Oct 2020) [§257.80(b)(5)]
- Annual Fugitive Dust Control Report [§257.80(c)]
- Run-on Run-off Control System Plan Update (Oct 2021) [§257.81(c)(3)]
- Inflow Design Flood Control System Plan Update Letter (June 2023) [§257.82(c)(3)]
- Structural Integrity Assessment [§257.73(a)(1) through (a)(4), and 275.73(c) through (f)]
- 免除, all three surface impoundments are incised with capabilities less than 20 acre-feet and heights less than 20 feet.
- Annual Surface Impoundment Report [§257.84(b)(3)]
- 免除, all three surface impoundments not subject to the periodic structural stability assessment, since capacity <20 acre-feet and height <20 feet.
- Annual Landfill Inspection Report [§257.84(b)(3)]
Groundwater Monitoring and Corrective Action
- Groundwater Monitoring System and Statistical Method Certification (Nov 2022) [§257.91(f) and §257.93(f)(6)]
- Annual Groundwater Monitoring and Corrective Action Reports [§257.90(e)]
- 2017 Groundwater Monitoring and Corrective Action Report (Jan 2018, amended September 2020)
- 2018 Groundwater Monitoring and Corrective Action Report (Jan 2019)
- 2019 Groundwater Monitoring and Corrective Action Report (Jan 2020)
- 2020 Groundwater Monitoring and Corrective Action Report (Jan 2021, amended March 2021)
- 2021 Groundwater Monitoring and Corrective Action Report (Jan 2022, amended February 2022)
- 2022 Groundwater Monitoring and Corrective Action Report (Jan 2023, amended March 2023)
- 2023 Groundwater Monitoring and Corrective Action Report (Jan 2024).
- Notification: Establishment of Assessment Monitoring and Constituents in Appendix IV of the CCR Rule Exceeded the Groundwater Protection Standard (amended April 18, 2018) [§257.94(e)(3)]
- Notification: Constituents in Appendix IV of the CCR Rule Exceeded the Groundwater Protection Standard [§257.95(g)]
- Notification: Initiation of Corrective Measure Assessment (June, 2018) [§257.95(g)(5)]
- Corrective Measures Assessment Report (Aug 2018) [§257.96(d)]
- Groundwater Remedy Selection and Design Semiannual Progress Reports [§257.97(a)]
Closure and Post-Closure Care
- Intent to Close CCR Landfill [§257.102(g)]
- Intent to Close CCR Surface Impoundments [§257.102(g)]
- Closure and Post-Closure Plan, Amended 2021 [§257.102(b)(2) and §257.104(d)(2)]
- Alternative Closure Annual Progress Report [§257.103(c)(2)]
- 2021-Oct Demonstration for Extension of CCR Landfill Closure Timeframe
- 2022-Oct Demonstration for Extension of CCR Landfill Closure Timeframe
Original Postings Superseded by Amendments
- 2022 Groundwater Monitoring and Corrective Action Report, dated January 2023
- 2021 Groundwater Monitoring and Corrective Action Report, dated January 2022
- 2020 Groundwater Monitoring and Corrective Action Report, dated January 2021
- Inflow Design Flood Control System Plan (Oct 2021) [§257.82(c)(3)]
- Groundwater Monitoring System & Statistical Method Certification Oct 2017 [§257.91(f) and §257.93(f)(6)]
- 2020 Alternative Closure Annual Progress Report, dated July 31, 2020
- 2020 Alternative Closure Annual Progress Report, amended August 5, 2020
- 2020 Alternative Closure Annual Progress Report, amended September 8, 2020
Contact Information
If you have any inquiries you may contact us.